Exercise 3. Choose the correct answer in the following.

1. Recent faults with machines have cost the company a great deal of __.

a) maintenance b) slack time c) downtime

2. Once the mock-up of the new design has been tested, we can build the ____.

a) prototype b) update c) set up

3. It's unprofitable to manufacture small quantities because of the machine___.

a) lead time b) set-up time c) sequence

4 The production manager has to produce a production______ for the next four weeks.

a) set up b) schedule c) output

5. Once the order has been agreed and production begun, the designer is still responsible for the_______.

a) work in progress b) workload c) back order

6. These items are produced together as one _____________.

a) cycle b) delivery c) lot

Ответы

Автор ответа: korunchyk
2

Ответ:

Exercise 3. Choose the correct answer in the following.

1. Recent faults with machines have cost the company a great deal of downtime.

a) maintenance b) slack time c) downtime

2. Once the mock-up of the new design has been tested, we can build the prototype.

a) prototype b) update c) set up

3. It's unprofitable to manufacture small quantities because of the machine lead time.

a) lead time b) set-up time c) sequence

4 The production manager has to produce a production schedule for the next four weeks.

a) set up b) schedule c) output

5. Once the order has been agreed and production begun, the designer is still responsible for the back order.

a) work in progress b) workload c) back order

6. These items are produced together as one lot.

a) cycle b) delivery c) lot